On-Site Magazine

Contract clarity and agreement a must in the digital age

By John Hyde   

Construction Law

The use of electronic contractual terms may create unexpected pitfalls in the construction industry.

(PHOTO: © VITTAYA_25 / ADOBE STOCK)

A digital link to terms may not be enough to make all linked conditions part of a contract. In a recent decision, the Manitoba Court of Queen’s Bench illustrated some of the potential issues associated with construction contracts that incorporate additional terms by referencing electronic documents.

This case is valuable for companies in the construction industry because it establishes the factors that courts will assess when determining the effect of important electronic contractual terms that were never seen by parties to the contract.

 

Overview

In Razar Contracting Services Ltd v Evoqua Water, the plaintiff, Razar Contracting Services, was a mechanical contractor hired to perform work on a potato processing plant in Manitoba. Upon selecting Razar to perform the work in question, the defendant, Evoqua Water, issued a two-page purchase order. The bottom of the first page contained a statement reading, “Unless otherwise agreed to in writing, Terms and Conditions apply to this purchase order.” A link to a website containing those terms and conditions was then provided.

Advertisement

Razar’s president was unable to access the website containing the terms and conditions. After a failed attempt to follow the link, the president took no further steps because he was under the impression that a subcontractor agreement would be entered into between the parties. Such an agreement was never executed, however.

Had the plaintiff been able to access the website at the bottom of the purchase order, they would have found an arbitration clause mandating that any disputes arising between the parties would be arbitrated in Pittsburgh, Penn. This clause would prove to be the main source of contention in this case.

It is common for contracts in the construction industry to incorporate additional terms into the agreement by referencing other documents. Furthermore, with the advancement of technology and the proliferation of electronic contractual documents, the number of pitfalls and potential grounds for conflict have increased exponentially.

Not long after the parties entered into the contract, Razar registered a lien on the project because of unpaid amounts and costs associated with delays.

In response, Evoqua Water filed a demand for arbitration as a means of recovering costs and expenses it claimed to have suffered because of Razar. Evoqua Water argued that both parties had agreed to resolve any matters by way of arbitration, as per the clause mentioned above. Prior to this dispute, Razar had no knowledge of the arbitration clause that Evoqua Water wished to rely upon. Naturally, Razar argued that it had never entered into any agreement to arbitrate disputes.

Razar then filed a lawsuit, which was the subject of this decision in the Manitoba Court of Queen’s Bench. As a consequence, Evoqua Water argued that the court did not have jurisdiction to hear the matter, due to the arbitration clause agreed to by the parties.

The central issue for the court to determine was whether a valid and binding arbitration agreement existed between the plaintiff and defendant.

 

What is an arbitration agreement, and what makes it enforceable?

In determining the effect of the arbitration clause at the centre of this dispute, the core piece of legislation the court considered was the International Commercial Arbitration Act (ICAA). Moreover, whenever the ICAA is applicable in a legal dispute, so too is the Model Law on International Commercial Arbitration (International Law).

According to the International Law, arbitration agreements are defined as agreements to submit all disputes arising between parties in a defined legal relationship to arbitration. Furthermore, the International Law stipulates that arbitration agreements must be in writing, such as a document signed by the parties or an exchange of documents providing a record of the agreement. As well, a contract that references an arbitration clause found in another document can be an arbitration agreement, as long as the contract is in writing and the reference serves to incorporate the clause into the contract.

In the construction industry, where the terms and conditions governing a single project can be found in numerous documents, references to other terms can lead to especially problematic consequences. Those concerns are exacerbated when contractual terms are in an electronic format, as various factors may make it more difficult to access and review important conditions associated with the contract.

Indeed, electronic contracts in the construction industry may lead to situations where firms will effectively have no knowledge of certain key terms and conditions purportedly governing the project they are working on. While it is easy enough to review a concise physical document containing terms and conditions, construction firms often do not have that luxury. As well, when there are electronic components to the contract, companies in the construction industry must be increasingly detail-oriented so as to ensure that they are able to review all aspects of the contract, sub-contract, or any working arrangement they will be entering into.

In the case at hand, Evoqua Water suggested that the arbitration agreement was indeed in writing pursuant to the aforementioned definition, as the purchase order issued was a document or communication indicating an agreement. In the alternative, Evoqua Water argued that the purchase order referred the plaintiff to a document that contained an arbitration clause, and that reference served to make the arbitration clause part of the contract. However, that “document” containing the arbitration clause was a website providing a dog’s breakfast of different terms and conditions that the plaintiff was never able to access.

Razar argued that no enforceable arbitration agreement existed, and the court agreed.

 

No valid and binding arbitration agreement

In beginning its analysis, the court acknowledged that the International Law’s definition of arbitration agreement required an exchange of documents whereby both parties agreed to refer disputes to an arbitrator. This did not happen in this case, as the plaintiff never saw the arbitration clause in question.

Furthermore, the court found that a reference to a website providing multiple different terms and conditions without any guidance related to dispute resolution was not a written arbitration agreement. As well, there was nothing to suggest that the plaintiff understood that it would be bound by the various terms and conditions.

At the same time, the court reasoned that there was no “meeting of the minds” between the parties with respect to an agreement to arbitrate. In addition to the fact that the Razar’s president never saw the arbitration clause, Evoqua Water also never drew anyone’s attention to the relevant terms and conditions mandating arbitration.

As a consequence, the court concluded that the parties did not enter into a valid and binding arbitration agreement.

The court’s analysis is beneficial to companies engaged in construction, as it demonstrates that they will not be beholden to a clause that they never had the opportunity to review, or that was not sufficiently brought to their attention. Given the nature of the construction industry and the proliferation of electronic contracts or contractual terms incorporated by reference, this is an important decision that serves to protect contractor interests.

 

The bottom line

While the court’s decision should indeed provide a sigh of relief for contractors in the construction industry, caution is still required when agreeing to contracts that incorporate additional terms by way of references to electronic documents. In an industry where several documents can contain a laundry list of terms and conditions applicable to a single project, construction companies need to ensure that they have a firm understanding of what they are agreeing to when accepting a contract.

Accordingly, we advise all in the construction industry to obtain expert legal advice if they have any concerns about entering into a contract, subcontract, or any other form of agreement to perform work on a project.

 

John Hyde

John Hyde
(Submitted Photo)

John Hyde is the managing partner at Hyde HR Law in Toronto. He advises management on all aspects of employment and labour law, including representation before administrative tribunals, collective agreement negotiation, arbitrations, wrongful dismissal defence and human rights.

He also assists clients in providing strategic legal and human resources advice on labour and employment matters arising out of complex mergers, acquisitions and the sale of businesses.

For more information about his firm or how to protect your construction company, please visit www.hydehrlaw.com.

Advertisement

Stories continue below